a 6 by 4 by 1.5 metre excavation in loam
- Length
- 6 m
- Width
- 4 m
- Depth
- 1.5 m
- Soil
- Loam
- Truck capacity
- 6 m³
- Side batter for stability
- 0%
Volume in the ground36
36 x 1.25; 45/6 rounded up
Open this exampleExcavation volume with the swell factor applied. A hole of 36 cubic metres does not produce 36 cubic metres of spoil: loosened earth expands by 10 to 50 percent depending on the soil, and that is what has to be carted away.
Also called: excavation calculator, cut and fill volume.
36 m³ in the ground becomes 45 m³ once dug, because loosened loam swells by 25%. That is 8 truck loads at 6 m³ each. Backfill shrinks when compacted, so more loose material is needed than the void it fills.
The volume in the ground, called bank volume, is the hole. What comes out is larger because digging breaks up the compaction, and the swell factor varies from about ten percent for sand to fifty for broken rock. Trucking is costed on loose volume, so estimating from the hole dimensions understates the haulage. The reverse applies to backfill: compacted fill shrinks, so more loose material is needed than the void it fills.
earth in the ground is compacted; digging it loosens it, so the volume to cart away exceeds the holeEach of these is asserted on every build. If a change to the engine ever moved one of these answers, the build would fail before the page could print it.
Volume in the ground36
36 x 1.25; 45/6 rounded up